3RD PROGRESS REVIEW SITE MEETING FOR BUSHENYI WATER SUPPLY AUGMENTATION PROJECT (WARUGO PROJECT)

Yesterday morning, AM Bushenyi , BM & BE – Ishaka joined Eng. Herbert Mujuni, Project Manager – Warugo Project in the 3rd site progress review meeting for the construction of Bushenyi Water Supply Augmentation Project. Other members present were the contractor’s team headed by Lyu Jintao – PM/Contractor’s Representative & C.O.W – NWSC.
The meeting started with site inspection and the contractor was commended for good quality works done so far.
The contractor is slightly behind schedule as physical progress is at 32% against time progress of 34% however, the contractor pledged to catch up in this month of May as rains are slightly reducing
Below are the highlights of the physical progress of works at different units;
1.
RAW WATER INTAKE & ACCESS ROAD
✅ Site clearing, Earth filling & construction of access road has been done.

  1. WATER TREATMENT PLANT
    ✅The contractor has completed civil works for flocculator /coagulator, backwash and Clear Water Tank
    ✅For the Clarifier; Formwork for 2nd Lift walls and Reinforcements are ongoing
    ✅For Filters; Concrete casting for first Lift walls are ongoing.
    ✅For Pump House; Casting of blinding concrete has been completed
    ✅ Laboratory & Stores; Site clearing & excavation to reduce levels completed
    ✅Staff Houses; Site clearing & excavation to reduce levels completed
  2. 600m3 STEEL RESERVIOR ON 1M DWARF WALLS
    ✅Site clearing, excavation to reduce levels, casting of blinding concrete completed
  3. RAW & CLEAR WATER TRANSMISSION MAINS
    ✅No activity has been done however some pipes have already been delivered on site.
  4. MECHANICAL & ELECTRICAL WORKS
    ✅Materials are under procurement.
    See pictures.