The scope of this project includes
Siting and drilling of borehole at Bweranyangi swamp-completed
Construction of pump and generator house-completed
Procurement and installation of solar pump set (Q=8m3/h, H=258m)-completed
Land purchase for the 60m3 masonry Reservior at Miti Hill-completed
Construction of 60m3 masonry Reservior at Miti Hill-completed
Chain link fencing for pump/generator house and Reservior-completed
Laying of 1km DN80 PN16 &1.5Km DN80 PN10 Pumping Main to the Reservior at Miti Hill – So far 1km has been laid & we expect to lay the remaining 1.5km in Quarter 2 and thereafter commissioning will take place.
The major objective of this project is to stabilize water supply in the villages of; Miti, Nyakatugunda, Irashaniro, Katenga, Ryanteretere and Bweranyangi.
SOURCE: NWSC BUSHENYI AREA MANAGER’S OFFICE