Irembezi project (Nyamiko booster construction)

This project will cover areas of Nyakabirizi and Irembezi villages.

                   Scope of works

          Construction of pump & generator house-completed

          Construction of 60m3 reinforced concrete sump-completed

          Construction of Attendant/guard house-completed

          Construction of chain link fencing around Nyamiko booster-completed

          Land purchase for the 60m3 masonry reservoir at Irembezi Hill-completed

          Laying of 3.2km DN100 PN10 HDPE pipes delivery main to the sump-call off order raised

          Laying of 2.9km DN80 PN16 HDPE Pumping main to Irembezi reservoir-call order raised

          Procurement of booster pump set-ongoing

          Umeme connection to Nyamiko booster-ongoing

          Laying of distribution mains; 5km DN80 PN10 HDPE pipes, 5km DN50 PN10 HDPE pipes & 2km DN40 PN10 HDPE pipes-call off order have been raised

SOURCE: NWSC BUSHENYI AREA MANAGER’S OFFICE